A 215 sq ft prefab ADU costs $33,000 to $52,000 installed on a US West Coast lot in 2026, and the factory unit is only 34–46% of that figure. Freight and duty add 23–30%, the foundation 6–15%, utility runs 8–15%, and permits with engineering 6–11%. Here is every line, priced.
Buyers get caught by the same gap: the quotation arrives with a unit price and a shipping estimate, and the project closes 40–70% above it. A pod leaves the factory complete, but not attached to the ground, connected to the grid, or approved by anyone. Those three things are site work, and site work is priced by your address, not your supplier.
What the unit price covers, and what it does not
A finished unit from our line arrives as a room. The FOB price includes the galvanised steel frame, insulated wall and roof panels, factory-fitted glazing, interior lining, a wet core with shower, basin and WC, a kitchenette, climate control, lighting on two circuits, and wiring terminated at one external connection point. On the M-Series the envelope is fixed at 3.5 m wide and 3.2 m high because both numbers are transport decisions before they are design decisions.
What the FOB price does not include is everything between the factory gate and a certificate of occupancy:
Export crating, inland haulage to Qingdao, ocean freight, marine insurance
Import duty, port charges, customs brokerage, ISF filing
Drayage from the port to your lot, plus any permit for an oversize load
A crane or telehandler, four hours typically, and the outrigger space it needs
Foundation: helical piles, a slab, or a stem wall
Utility laterals: water, sewer or septic, electrical conduit, and a sub-panel
Soils report, stamped structural and energy calcs, plan review, permit fees
Steps, deck, skirting, downpipes, landscaping reinstatement
On the worked example below, the unit is $14,200 FOB and the installed total is about $38,500. The gap is $24,300, and no single line in it is larger than the duty.
Freight, duty and the delivered number
This is the build-up for one 20 m² unit to a Los Angeles address, at rates in force in late 2026. Freight is quoted as a share of a 40HQ carrying two kits; a single kit in a box carries the whole container charge.
| Line | USD | Basis |
|---|---|---|
| Unit, FOB Qingdao | 14,200 | Mid-range 20 m² specification |
| Export crating and haulage | 380 | Per kit |
| Ocean freight | 3,400 | Half of a 40HQ at $6,800 |
| Marine insurance | 75 | 0.4% of CIF |
| Duty | 5,737 | 40.4% of FOB |
| Port charges, ISF, broker, clearance | 650 | Per shipment |
| Drayage to site, 120 km | 780 | Flatbed plus escort allowance |
| Crane, 4 hours | 900 | Includes travel |
| Delivered to the pad | 26,122 | Before foundation and utilities |
Duty breaks budgets because it is large and it moves. Steel modular units have been classified under HTS 9406.20 at 2.9% MFN, and the China-specific duties have changed repeatedly since 2018. Here 2.9% MFN plus 25% Section 301 plus a 12.5% surcharge is 40.4% of FOB — $5,737, more than the freight. Confirm the classification and Chapter 99 treatment with your broker in writing before the deposit.
Container geometry sets freight per unit and therefore the size you should buy. A 40HQ measures 12.03 × 2.35 × 2.69 m internally, with a 2,340 × 2,585 mm door aperture and 26,000–28,000 kg payload. A flat-packed 20 m² kit loads two to three to a box; an assembled 12 m unit does not pass the door. Rates through 2026 have run $2,600–$7,500 per 40HQ, so plan at $3,000–$3,500 per kit where two share. The clearance sequence is in our guide to shipping a capsule overseas.
Foundation: three options, priced per unit
A pod is a point-loaded structure, so the foundation question is how many piles and how deep, not how thick a slab. For a 215–452 sq ft unit, the three viable options price very differently, and the cheapest is not always the slab.
| Option | Typical 2026 cost | Cost for a 30 m² unit | When it is the right answer |
|---|---|---|---|
| Monolithic slab on grade | $12–$25 per sq ft | $3,900–$8,100 | Flat lot, slope under 5%, stable soil, unit will never move |
| Stem wall with crawlspace | $20–$35 per sq ft | $6,500–$11,300 | Mild slope, plumbing access needed, frost depth to clear |
| Helical piles, 6–10 piles | $500–$1,500 per pile | $3,000–$15,000 | Slope, expansive clay, fill soil, tight access, removable later |
Helical piles are usually right for an imported pod, for three reasons beyond price. They install in one to three days with no curing, so the crane is not idle waiting for concrete. They need a mini-excavator, not a concrete truck, which matters when the only route to the backyard is a 1.2 m gate. And they can be removed, which keeps a leasehold reversible.
Two documents decide which row you land in. A geotechnical report costs $500–$5,000 depending on region — $1,500–$4,000 is typical in Southern California — and it tells your engineer the bearing capacity and whether the clay is expansive. Stamped foundation design for a specific unit then costs $1,500–$2,500. Skipping the soils report to save $3,000 is how a $2,400 pile allowance becomes a $25,000 over-excavation after the first inspection.
The structural assumptions behind any pod are site-specific: wind, snow and seismic loads are set by your location, not by the factory. Units are engineered to meet typical requirements, and we supply the design statement showing which loads were used so your engineer of record can check them against local code. Acceptability is a determination for your building department, not for us.
Utility runs: the line that varies most
Two identical pods can differ by $20,000 on utilities, because distance to the main house, sewer invert depth and spare panel capacity are fixed by the existing house, not the new unit.
| Run | Burial depth | Typical cost | 50 ft run |
|---|---|---|---|
| Electrical feeder in rigid PVC conduit | 18 in (24 in under a driveway) | $8–$15 per linear ft | $400–$750 |
| Potable water, 3/4–1 in PEX | 12 in, or 6 in below frost line | $25–$45 per linear ft | $1,250–$2,250 |
| Sewer lateral, 3–4 in, 1/4 in per ft fall | 24–36 in | Quoted with the trench | Included below |
| Combined trench, all three in one cut | Per the deepest service | $40–$85 per linear ft | $2,000–$4,250 |
| 200 A panel upgrade, if no spare capacity | — | $2,500–$4,500 | — |
| New sewer tap with street cut | — | $8,000–$25,000 | — |
| Septic system, where no sewer exists | — | $15,000–$30,000 | — |
The combined-trench number is the one to budget from: $40–$85 per linear foot for excavation, pipe, conduit and backfill, which for the typical 40–60 ft backyard run comes to $6,500–$14,000. Digging one trench for all three services instead of three separate cuts is the single largest saving available on this line, and it requires deciding the unit position before the foundation is laid — not after.
Two constraints catch imported units. The sewer invert must sit below the pod's waste outlet with a 1/4-inch-per-foot fall over the whole run; on a shallow or long connection you need a lift station at $8,000–$15,000 instead of gravity. And the electrical build must match the destination: 110/220 V split-phase for North America, not the 220 V single-phase used in most export markets. Put voltage on the purchase order, because rewiring a finished unit costs more than specifying it correctly.
Permits, fees and the state thresholds that decide them
Permit and engineering costs for a small ADU run $3,000–$15,000, of which the fee schedule is often the smaller part. The larger variable is whether your state forces a ministerial approval path or leaves you in discretionary review, where a neighbour's objection can add a year.
| State | Controlling law | What it requires as of 2026 |
|---|---|---|
| California | Gov. Code §§66310–66342; AB 956 and SB 1117, signed 29 Sep 2026, effective 1 Jan 2027 | Ministerial approval of two detached ADUs up to 800 sq ft each on a single-family lot; no impact fees on the first 750 sq ft of each unit |
| Washington | HB 1337 (compliance due 30 Jun 2025); HB 1345 (effective 11 Jun 2026) | Two ADUs per lot in growth areas, minimum 1,000 sq ft must be allowed, impact fees capped at 50% of the primary unit; counties may allow one detached ADU outside growth areas |
| Colorado | HB 24-1152 (effective 30 Jun 2025) | One ADU by right per single-family lot in covered metro jurisdictions; HOAs cannot prohibit them there |
| Oregon | HB 2001 (2019) | One ADU per single-family lot in cities over 2,500 people |
| Maine | LD 2003 (2022) | ADUs allowed in all municipalities, attached or detached |
Footprint matters here in a way that surprises buyers. A 20–42 m² unit is 215–452 sq ft, which sits under California's 800 sq ft ministerial cap and under the 750 sq ft impact-fee threshold. In practical terms that means a pod this size can take the cheapest approval path available in the state and, on a California lot, attract no impact fee at all. A 700 sq ft prefab does neither.
State law sets the floor, not the answer. Setbacks, height, lot coverage, parking and fire separation are local, and no preemption overrides a hillside or wildfire overlay. Put the use class, the foundation permit question and the energy code requirement to your planning department in writing before you order. Our five backyard ADU scenarios show how those answers change the design.
Four sizes, costed to the site
Installed totals below use the same build-up throughout: unit, freight, duty, port, drayage, crane, foundation, utility run, permits and engineering, plus an 8% contingency. US West Coast destination, as of 2026, standard specification.
| Model | Floor area | FOB per unit | Installed total | Per sq ft installed |
|---|---|---|---|---|
| M10 flat-pack | 20 m² / 215 sq ft | $11,800–$17,500 | $33,000–$52,000 | $153–$242 |
| M30 | 24.5 m² / 264 sq ft | $15,500–$19,500 | $40,000–$59,000 | $152–$223 |
| M50 | 30 m² / 323 sq ft | $17,000–$24,000 | $41,000–$61,000 | $127–$189 |
| M42 | 42 m² / 452 sq ft | $21,000–$33,000 | $61,000–$76,000 | $135–$168 |
Read the third and fourth columns together and one conclusion is unavoidable: the 24.5 m² and 30 m² units install within about $1,500 of each other. The extra 5.5 m² is close to free, because the wet core, the electrical assembly and the crane are fixed costs that do not shrink with the floor. Buyers who choose the smaller unit to save money usually pay the same and lose the room.
What the table cannot show is the fit. A 20 m² pod is one room with a bathroom — right for a couple or a rental, wrong for a family. A 42 m² unit is the smallest that works as a full-time one-bedroom. The 20 m² M10 flat-pack capsule is the entry point and the cheapest to land per container; the 30 m² M50 is the volume seller for backyard rental; the 42 m² M42 replaces a house rather than a room; the 16.8 m² Apple Cabin covers the bottom where a studio is enough.
How to compare two ADU quotes in twenty minutes
Two quotations for the same footprint are rarely comparable, because each is silent about a different scope. Ask these twelve questions and mark each answer included, excluded or buyer.
Does the drawing set name your jurisdiction, or is it a generic plan?
Are structural, energy and foundation calculations stamped for your state?
Is the foundation designed, supplied and installed, or designed only?
What utility allowance is written into the price, in linear feet?
Is the crane included, and for how many hours?
Are permit fees a pass-through or a fixed line?
Who submits the permit, and how many plan-check revision cycles are covered?
Is the panel upgrade inside the price or assumed unnecessary?
Who signs off the final inspection and the certificate of occupancy?
Is contingency stated, and who holds it?
Was a site visit done before the fixed price was issued?
Which warranty applies to the shell, the panel coating, the electrical and the wet core — and for how long?
Quotations that fail more than three of those lines are not fixed prices; they are estimates with a deposit attached. Four phrases are worth treating as warnings rather than reassurance: "permit-ready" without a named jurisdiction, "turnkey" without a written scope exhibit, any quote with no foundation line at all, and a utility allowance described as "first 25 linear feet" when your run is 50.
One comparison is worth more than the rest: ask both suppliers for the installed total to your address, not the unit price. Our landed cost guide shows how that number is assembled line by line, and any supplier who cannot produce it in writing within a day has not costed your site.
Frequently asked questions
How much does a prefab ADU cost installed in 2026?
For a 215–452 sq ft unit on a US West Coast lot, $33,000 to $76,000 installed, which is $117 to $242 per sq ft. The factory unit is 34–46% of that total; freight, duty, foundation, utility runs and permits make up the rest.
Is a prefab ADU cheaper than site-built?
Usually 10–20% cheaper on hard cost, and materially faster: 90–120 days from order to occupancy against 8–14 months for site-built. The saving is smaller than the brochure implies because site work is the same either way, and on a difficult lot site work can exceed the unit cost.
Do I need a concrete slab for a prefab ADU?
No. Most pod units sit on six to ten helical piles at $500–$1,500 each, which install in one to three days without curing and can be removed later. A slab at $12–$25 per sq ft is cheaper on flat, stable ground and is the better choice where the unit will never move.
Can a prefab ADU share utilities with the main house?
In most jurisdictions, yes: water and sewer can tap the existing laterals and power can run from a sub-panel, provided the main panel has spare capacity. A 200 A panel upgrade at $2,500–$4,500 is the most common surprise, and separate meters are usually required if a tenant pays their own utilities.
Does a prefab ADU need a building permit?
Yes, in every US jurisdiction we ship to. A factory-built unit still needs a foundation permit, utility permits and a final inspection before occupancy. The advantage of a state preemption such as California's AB 956 is a ministerial path and a deadline, not an exemption.
What is the smallest prefab ADU that can be permitted?
There is no national minimum; most ordinances set a floor between 150 and 300 sq ft of interior living space, and some set none. A 16.8–20 m² unit at 181–215 sq ft sits above the common floor, but confirm the local minimum with your planning department before ordering.
Send the destination port, the lot's slope and the distance from the main house to the proposed pad. We will return a landed cost to your address, a foundation option that matches the soil you describe, and the container load plan — the three inputs that decide whether the quotation you have is a budget or a guess.