For on-site assembly of one standard space capsule:
Minimum 3 workers (experienced): complete main structure in 1 day.
Standard team of 4 workers: finish assembly & basic commissioning in 4–8 hours; no large crane needed.
Multi-unit projects (5–10 capsules): 6–8 workers recommended; full installation & system connection in 2–3 days.
Note: High factory prefabrication, bolted connections & quick-connect utilities on site; no welding required, saving labor and time。